Cost Analysis

The county's public case for the November 3, 2026 bond centers on a claim that building new saves $69.4M over 20 years compared to the alternative. This page examines that claim using primary source documents: the FY27 budget, Sheriff's control sheets, and the Shive-Hattery reports themselves.

All per-diem and operating figures are from the FY27 proposed budget (function 1050) unless otherwise noted. Debt-service figures use the county's financing matrix (Piper Sandler & Co., July 29, 2026 work session packet): the 12-year scenario the Board discussed prices $94.5M at a 4.45% all-in interest cost with $30.2M of total interest. The repayment term is not fixed in any adopted document; the matrix spans 10 years ($25.0M interest) to 20 years ($51.6M). Where a single scenario is needed, this page uses the 12-year row. National benchmarks are flagged as estimates. (function 1050) unless otherwise noted. Debt-service figures use the county's financing matrix (Piper Sandler & Co., July 29, 2026 work session packet): the 12-year scenario the Board discussed prices $94.5M at a 4.45% all-in interest cost with $30.2M of total interest. The repayment term is not fixed in any adopted document; the matrix spans 10 years ($25.0M interest) to 20 years ($51.6M). Where a single scenario is needed, this page uses the 12-year row. National benchmarks are flagged as estimates.
~35

In-house ADP per 100,000 JoCo residents (FY22–FY25 avg; ~53/100K total in-custody). See Part 1 →

+61%

Sheriff general-fund budget growth, FY22–FY27 proposed ($11.6M → $18.7M) — before any bond construction. Sources: FY24, FY25 Budget Books; FY27 Tax Calculation.

$120–146M

Total repayment authorized by a yes vote at the county's estimated yields — a range this wide because no published county material states a repayment term. The rate is necessarily unknown until the bonds price after the election; the term is a policy choice the Board has only informally made (12 years, August 5). See Part 5 →

Part 1

Per-Day Costs

$315
In-house operating cost per person per day
(FY27 budget, function 1050, excluding OoC pass-through)
$60
Out-of-county transfer rate paid
(Linn County and Henry County contracts, 2024–25)
Linn County charged U.S. Marshals $86–$140/day for the same beds
~$547/day
Reference point: debt service (~$339/day at 84 ADP, 12-yr scenario) plus current JoCo per-person operating cost at 84 ADP ($208/day)
No pro-forma operating budget for the new facility has been published

The $315/day in-house figure

The FY27 Total Expenses Budget breaks out the Sheriff's Office by function code. Function 1050 is the jail. Its total is $7,186,029, which includes $800,000 for SC349 — Inmate Housing, Out of County. That line is a pass-through to other counties, not a cost of operating the Johnson County jail. Removing it yields an in-facility operating cost of $6,386,029.

Divided by the FY26 partial in-house ADP of 55.62 × 365 days: $6,386,029 ÷ 20,302 = ~$315/day per person.

Personnel and benefits account for 89% of that cost (FY27 Total Expenses Budget, Function 1050: $5,689,901 personnel+benefits ÷ $6,386,029 in-facility cost).

Show FY27 Function 1050 line-item budget
Line item FY27 budget
SC100 Salaries of Regular Employees$3,708,064
SC101 Wages of Temporary & Part-time$120,739
SC104 Overtime & Shift Pay$173,710
SC111 IPERS (pension)$424,813
SC113 Employee Group Health Insurance$912,392
SC114 Allowances to Employees$11,520
SC117 Other Benefit Programs$45,760
Social Security$292,903
Total personnel and benefits~$5,689,901
SC230 Commodities — Food & Provisions$331,000
SC231 Clothing & Dry Goods$11,000
SC234 Kitchen Supplies$6,500
SC291 Medical & Laboratory Supplies$5,000
SC294 Wearing Apparel & Uniforms$30,000
SC302 Primary Treatment$18,000
SC306 Prescription Medication/Vaccines$80,000
SC349 Inmate Housing — Out of County$800,000
SC378 Contracted Coordination Services$13,000
SC413 Mileage & Other Travel Expenses$47,100
SC422 Educational & Training Services$84,625
SC447 Repair & Maintenance — Misc.$16,041
SC453 Rentals — Office Equipment$5,137
SC634 Household & Institutional$4,200
SC636 Office Equipment & Furniture$6,650
Other misc.~$194,875 (est.)
Total non-personnel~$1,496,128
Function 1050 Total$7,186,029

Source: JoCo FY27 Total Expenses Budget, CC08 Sheriff, Function 1050 (Jail). SC349 ($800,000) excluded from the in-facility per-diem calculation as an intergovernmental pass-through.

The 65-bed cap in historical context

Sheriff Kunkel stated in May 2024 that he caps in-house population at approximately 65. The monthly control sheets support two readings of that cap. Pre-COVID stable years (FY17–FY19) show an average in-house ADP of approximately 62.2/day — just below 65, consistent with a cap that was being approached but not exceeded. Post-COVID stable years (FY22–FY26 partial) show an average of approximately 55.5/day — roughly 10 below the stated cap. The two readings are: (a) the cap is unchanged at 65 and post-COVID demand simply dropped; or (b) the cap was tightened de facto after COVID, and the 65 figure reflects an earlier, looser practice. Distinguishing between them requires daily peak data. The monthly control sheets report monthly averages only; daily peaks are not published.

The $60/day out-of-county rate

Johnson County pays $60/day to Linn County (Cedar Rapids) under a 2024 agreement with a 4% annual escalator, and $60/day to Henry County from FY2025 (up from $50/day). Washington County charges the same $60/day, per the January 2026 State inspection sheet. The Sheriff's snapshot (slide 10) lists Cedar at $65/day and Clinton at $55/day; the Lee County rate is not publicly reported.

Johnson County's claims registers confirm the Washington County rate to the penny. "Inmate Housing Dec25" was $12,900: exactly 215 prisoner-days × $60. "Inmate Housing Jan26" was $6,420: exactly 107 prisoner-days × $60 (claims registers, January 29 and February 12, 2026 formal agendas). The posted rate is the paid rate.

The $60/day figure is a transfer rate between counties — what intergovernmental negotiation produced — not necessarily a measure of what it costs to run a jail. Linn County previously charged the U.S. Marshals Service $86–$140/day for the same beds (The Gazette, 2024).

Comparing Johnson County's average in-house cost ($315/day) directly to the $60 transfer rate conflates a fully-loaded average cost with a sub-cost intergovernmental rate. The two figures are not measuring the same thing.

The receiving jail has room. Washington County's jail was built in 2007 and holds 84 beds. On inspection day, January 29, 2026, 23 beds were occupied, leaving 61 empty beds about 30 miles from Iowa City. The census is a one-day snapshot. The same State inspector who inspects the Johnson County jail inspected Washington County's and marked zero non-compliance items. The inspection report and cover letter are available for download.

The $960K standing budget — the OoC pressure point is partly an artifact

The OoC budget line has been static at $960,000 across every published year through FY26. Sheriff Kunkel confirmed at his November 2024 budget presentation:

Standing budgeted amount of $960,000 — in place before I came into office. This number can fluctuate over time, always kept budgeted amount static in case of emergency.

Sheriff Brad Kunkel, Sheriff's Office FY26 Budget Presentation, slide 20 (delivered to Board of Supervisors, November 2024)

Kunkel took office January 2017. FY23–FY25 actuals were $331K–$440K — between 35% and 46% of budget. The FY27 line drops to $800K with no published justification. The "$800K projected OoC pressure" framing in bond-justification materials uses a budgeted number two-to-three times what the County has actually spent in any year since 2015. Actual OoC spending peaked in calendar year 2010 at $1.89M and has trended downward since 2015.

Out-of-county housing costs for people held, FY17–FY27 Bar chart showing Johnson County out-of-county housing actual costs from FY17 through FY25, with FY26 partial-year actual (6 months), and the FY27 budgeted amount of $800,000. FY27 is 2.6 times the FY24 actual of $303,120. A reference line marks the $960K standing budget held static from FY17 through FY26 — actuals have been 35–46% of that figure. $0 $200K $400K $600K $800K $1.0M $960K standing budget (FY17–FY26) (6 mo.) FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 partial Out-of-county housing cost
Johnson County out-of-county inmate housing costs, FY17–FY27. Solid bars are full-year actuals; the hatched FY26 bar is a six-month partial; the FY27 outlined bar is budgeted. The $800K FY27 figure is 2.6× the FY24 actual of $303,120.
Show FY17–FY27 out-of-county housing history
FY Actual spend OoC ADP Implied per-diem
FY17$451,08523.52~$52/day
FY18$827,10539.73~$57/day
FY19$648,75036.54~$49/day
FY20$531,05528.89~$50/day
FY21$302,15516.35~$51/day
FY22$459,20527.28~$46/day
FY23$326,80518.28~$49/day
FY24$303,12016.98~$49/day
FY25$440,38021.85~$55/day
FY26 (partial, 6 mo)$240,31924.49~$54/day
FY27 (budgeted)$800,000

Source: Johnson County Sheriff's Office control sheets (FY17–FY26 partial). Implied per-diem = actual spend ÷ (OoC ADP × 365). FY27 is budgeted, not actual. The implied per-diem rose from ~$46–$52 (FY17–FY23) to ~$54–$55 (FY24–FY26), consistent with contract rate increases. FY27 budget of $800K is ~2.6× the FY24 actual.

Comparison table

Housing type Rate Source
JoCo in-house (FY27 budget basis) ~$315/day JoCo FY27 budget, function 1050
JoCo pays Linn County $60/day 2024 contract (4% annual escalator)
JoCo pays Henry County $60/day FY2025 contract
JoCo pays Washington County $60/day Jan 2026 State inspection sheet; claims registers (exact $60 multiples)
Linn County charged U.S. Marshals (prior) $86–$140/day The Gazette, 2024
Iowa state prisons (avg) ~$116/day Iowa Legislature FY data

† Iowa state prisons house longer-term sentenced incarcerated people with different programming, medical, and security cost structures than county jails. The $116/day figure is included as a reference benchmark only and is not directly comparable to county jail operating cost.

The Sheriff is already cutting per-position cost via civilianization — independent of any new facility

Job Bulletin #00852 (Detention Officer, posted May 5, 2025) lists the wage at $29.68/hour — approximately $61,700 base salary. The position is female-only under Iowa Code §356.5 BFOQ. In his FY26 and FY27 budget planning forms, Sheriff Kunkel documented the per-position savings from civilianizing Deputy Sheriff positions through attrition:

We will continue operating under the new jail staffing model by filling open deputy sheriff positions with civilian detention officers. This is saving an estimated $14,000 in salary and benefits plus an additional $10,000+ in ILEA expenses per position.

Sheriff Brad Kunkel, FY27 Budget Planning Information, December 15, 2025

Total documented savings: ~$24,000/year per civilianized position. This is happening now, independent of any bond-funded facility. Two implications: (1) the elevated per-diem cost of the existing jail is in part a function of the staffing model, which the Sheriff acknowledges can be tightened; (2) any bond-campaign framing that treats the current operating cost as fixed and inflated by aging infrastructure ignores cost reductions the Sheriff has already identified and is implementing.

ADP in context: Johnson County vs. population

Normalizing ADP to county population helps contextualize the facility's actual use. Using U.S. Census Bureau Vintage 2024 Population Estimates for Johnson County (July 1 of the fiscal year start) and control-sheet ADP:

FY JoCo population (July 1) In-house ADP In-house per 100K Total in-custody ADP Total per 100K
FY22 155,035 50.99 ~33 85.00 ~55
FY23 156,915 57.21 ~36 81.71 ~52
FY24 157,528 56.82 ~36 81.15 ~52
FY25 160,080 56.70 ~35 84.08 ~53

Population: U.S. Census Bureau, Population Estimates Program (PEP) Vintage 2024; July 1 estimates for Johnson County, Iowa (FIPS 19103). 2021–2023 from Vintage 2024 PEP; 2024 = 160,080 (Census QuickFacts). ADP from Johnson County Sheriff's Office control sheets. Total in-custody includes in-house + out-of-county housed + electronic monitor. FY21 (COVID recovery year) excluded; in-house ADP of 34.78 would yield ~22/100K. Table ends at FY25 because the Sheriff's dashboard "12 Month Trend" (Jun 2025–May 2026) is a rolling window straddling FY25 and FY26 — not a full fiscal year. See the Overview ADP section for the most recent rolling trend figures.

Part 2

Capital Costs

$788K
per bed upper bound — the $94.5M adopted bond ÷ 120 built-out beds; the bond covers jail and Sheriff's Office, not jail only (see table below)

The adopted bond totals $94.5M for the combined jail and Sheriff's Office facility. Because that covers both the jail and the SO, dividing the full bond by jail beds overstates per-bed cost. Shive-Hattery Vol. I (August 2024) split the combined facility at ~61% jail / ~39% law enforcement by cost; the county's bond site states the jail is 45% of the building by floor area; Sheriff Kunkel has publicly characterized the jail as approximately half the project. Per-bed cost varies substantially depending on which share is used:

Scenario Beds Capital basis Cost per bed
Full $94.5M ÷ 120 built-out beds (upper bound) 120 $94.5M ~$788K/bed
Full $94.5M ÷ 140 beds (incl. 20 shelled) 140 $94.5M ~$675K/bed
61% jail share (Vol I split) ÷ 120 beds 120 ~$57.6M ~$480K/bed
50% jail share (Sheriff Kunkel) ÷ 120 beds 120 ~$47.3M ~$394K/bed
Jail-only (Shive-Hattery Vol I 2024 estimate) 120 ~$48.88M ~$407K/bed

Confirmed post-2022 comparables (all combined Sheriff's Office + jail unless noted):

Facility Built beds Cost Per bed Notes
Warrick County, IN (opened 2026) ~300 ~$50M final ~$167K Scale: ~2.5× JoCo's 120; per-bed cost falls with size. Source: WFIE/14News, June 24, 2026.
Kewaunee County, WI (2023) 58 (85 expandable) $25.6M approved; ~$33M rebid ~$441K–$569K Includes jail + 911/dispatch + Sheriff's Office (40,500 SF). Rebid after inflation. Source: Kewaunee County Star-News; WBAY, Aug 2023.
Otsego County, NY (2025 estimate) 96 $64.5M total / $53.7M construction $672K total / $559K construction Maximum-security; carries higher cost than standard county jail.
JoCo proposed (jail-only component) 120 ~$48.88M (Shive-Hattery 2024) ~$407K Does not include Sheriff's Office. Full $94.5M bond ÷ 120 beds = $788K.

Per-bed cost is strongly size-driven: Warrick at ~300 beds comes in at ~$167K/bed; Kewaunee at 58 beds reaches ~$569K/bed; Otsego at 96 beds (maximum-security) reaches $672K/bed. JoCo's jail-only component at ~$407K/bed sits between Kewaunee and Warrick, adjusted for scale. The full $94.5M ÷ 120 = $788K figure includes the Sheriff's Office building and is not directly comparable to jail-only per-bed figures. Per-bed cost falls if the 20 shelled beds are included or if the facility runs at higher occupancy. All comparables should be verified against primary construction documents.

The per-square-foot trajectory: $752.61 to $850 in two years

The County's stated jail construction rate has risen twice since Vol. I. At the July 9, 2026 CJCC meeting, Sheriff Kunkel asked Shive-Hattery "is it $800? $850 a square foot?" and Shive-Hattery's Michael Lewis confirmed "$850 a square foot versus just about $600." The $850 is the jail side; the roughly $600 is the sheriff's-office side.

Date Stated jail rate Source Stated dollar-year basis
August 2024 $752.61/SF Shive-Hattery Vol. I "Escalated to 2025 dollars"
August 14, 2025 $800/SF Joint-feasibility presentation "Projected to 2027 dollars"
July 9, 2026 $850/SF CJCC meeting (Kunkel/Lewis exchange, Granicus clip 3697) Not stated

The chart below compares the County's stated rates against the Turner Building Cost Index, a standard national index of non-residential construction cost, rebased so its 2024 annual average equals the Vol. I rate of $752.61/SF. The index implies about $806/SF by mid-2026. The County's stated $850 runs 5 to 6 percent above construction inflation.

County-stated jail cost per square foot vs. the Turner Building Cost Index, 2024–2026 Line chart, mid-2024 to mid-2026. A line shows the Turner Building Cost Index rebased to $752.61 per square foot at the 2024 annual average, rising to about $806 by mid-2026. Three dots show the County's stated jail rates: $752.61 in August 2024, $800 in August 2025, and $850 in July 2026. The $850 point sits 5 to 6 percent above the rebased index line. $740 $780 $820 $860 Aug 2024 Feb 2025 Aug 2025 Feb 2026 Jul 2026 TCCI-implied ≈$806/SF 5–6% above the index $752.61 Vol. I (Aug 2024) $800 Aug 14, 2025 presentation $850 July 9, 2026 CJCC County-stated jail $/SF Turner Building Cost Index, rebased to $752.61 at the 2024 average
County-stated jail cost per square foot (dots) against the Turner Building Cost Index rebased to $752.61 at the 2024 annual average (line). Index source: Turner Construction Cost Index, turnerconstruction.com/cost-index (Q1 2026 report).

The same decomposition applies to the total. The combined estimate was $79.75M for 111,300 GSF in August 2024. The adopted bond cap is $94.5M for 118,500 SF, an increase of 18.5%. The Turner index rose about 7.3% over the same window. Floor area grew 6.5% (111,300 to 118,500 SF). Inflation and floor-area growth together explain about $91M. The rest is rate and scope mix.

The building has grown at each stage of planning: 35,000 SF, then 80,000 SF, then 118,500 SF (trajectory stated on the record by Supervisor Fixmer-Oraiz, July 9, 2026). The current building is 27,000 SF per Shive-Hattery Vol. I; the proposal is about 4.4 times the existing footprint. (The county's bond site says the current building is 28,500 SF, contradicting the county's needs assessment; at that figure the ratio is 4.2.) A cost estimate update on the 118,500 SF basis was announced at the July 9 CJCC meeting. No updated buildup has been published; the adopted cap is $94.5M.

Annualized capital cost per person per day

At $94.5M under the 12-year scenario, total debt service is $124.7M ($94.5M principal + $30.2M interest, per the Piper Sandler matrix), averaging ~$10.39M/year. That debt service, divided across occupied beds, produces the following capital cost per person per day — before any operating costs: At $94.5M under the 12-year scenario, total debt service is $124.7M ($94.5M principal + $30.2M interest, per the Piper Sandler matrix), averaging ~$10.39M/year. That debt service, divided across occupied beds, produces the following capital cost per person per day — before any operating costs:

Occupancy Prisoners/day CapEx per person per day
Current in-house ADP 56 ~$508/day
Full managed ADP (incl. OoC and EM) 84 ~$339/day
Full 120-bed capacity 120 ~$237/day

The Shive-Hattery Supplemental Life Cycle Cost Analysis states that the Build New scenario operates with 24 staff positions but does not publish a pro-forma operating budget — no per-person or annual operating cost figure appears in the document. The only primary-source-grounded all-in figure available is debt service plus current JoCo operating cost scaled to 84 ADP: $6.386M ÷ (84 × 365) = ~$208/day operating + ~$339/day debt service = ~$547/day.

This is a reference point, not a projection: it asks "what would today's operating cost per person be at the new facility's expected population?" Shive-Hattery's Build New scenario specifies 24 FTE, compared to the current jail's staffing embedded in the $5.69M personnel budget. Whether 24 FTE at a modern direct-supervision facility produces lower per-person operating cost than today cannot be evaluated without a published operating pro-forma. That document has not been released.

The debt service figure is fixed — it does not change with occupancy. The per-person share of that fixed cost falls as more people occupy the facility:

Occupancy ADP Debt service/p/day
Current operational cap 65 ~$438/day
Current total managed ADP 84 ~$339/day
Initial built-out capacity 120 ~$237/day

Debt service calculated as ~$10.39M/year average ($124.7M total under the 12-year Piper Sandler scenario) divided by occupancy × 365. The term is not fixed in any adopted document; at 20 years the annual average falls to ~$7.3M and the total rises to $146.1M. The 65-bed "operational capacity" is the Sheriff's figure used by Shive-Hattery; its basis has not been established in any published document (see Section 1).

Part 3

Built to the Minimum, Designed for Growth

We're looking for specific situations that align exactly … with what the Iowa Jail Standard requires.

Shive-Hattery presentation, CJCC meeting, July 9, 2026, 20:48 (Granicus clip 3697)

The schematic design presented at the July 9, 2026 CJCC meeting (Granicus clip 3697) treats the two halves of the building differently. The jail side is engineered to the Iowa Jail Standards floor (Iowa Administrative Code 201—50.8, the new-construction checklist the State Inspector uses). The sheriff's-office side has no code minimums and is where expansion happens.

The jail side against the state floor

Element IAC 201—50.8 minimum Current jail As designed Margin (proposed)
Single cell (occupied more than 10 hours/day)
Source (clip 3697, 23:10)

"It works out to be 70 square feet in the cell." — Shive-Hattery presentation, CJCC meeting, July 9, 2026 (Granicus clip 3697, 23:10)

70 SF [§50.8(1)a] ~70 SF gross
Note

The county's bond site states the current cells are “approximately 70 square feet.” The current jail (built 1981) is governed by the grandfathered §50.5 regime, not §50.8. A 70 SF single cell passes the §50.5 inspection checklist.

70 SF Zero
Two-person cell (occupied more than 10 hours/day)
Source (clip 3697, 23:14 and 24:20)

"A two-person cell … works out to be 92 square feet." — Shive-Hattery presentation, CJCC meeting, July 9, 2026 (Granicus clip 3697, 23:14). The calculation (clip 3697, 24:20): 2 occupants × 35 SF unencumbered = 70 SF, plus ~22 SF consumed by toilet, bunks, writing surface, and stool ≈ 92 SF gross. The 35 SF figure here is the §50.8(1)b cell standard; the identical figure at §50.8(2)d governs dayrooms and is stated per prisoner exclusive of fixtures — a separate requirement.

35 SF unencumbered per occupant [§50.8(1)b] ~70 SF gross (double-bunked)
Note on compliance

The current jail double-bunks two prisoners in the same ~70 SF cells. Whether that passes §50.5 depends on hours in the cell: ≤16 hours/day requires 60 SF for two (40 + 20), so 70 SF complies; >16 hours/day requires 80 SF (50 + 30), so 70 SF does not. The state inspector has found zero non-compliance items in both 2025 and 2026, which implies the ≤16-hour condition is met. No published document states the actual hours-in-cell figure or identifies which threshold the inspector applied.

92 SF gross (70 SF unencumbered + ~22 SF fixtures) Fixtures only vs. standard; 92 SF vs. ~70 SF current
Cell ceiling 7 ft [§50.8(2)a] Not published 8 ft +1 ft
Dayroom (4-bed unit)
Source (clip 3697, 22:34)

"If all four people are out in the day room, it's good to have a little bit of extra space." — Shive-Hattery presentation, CJCC meeting, July 9, 2026 (Granicus clip 3697, 22:34; standard stated at 22:46)

35 SF per occupant = 140 SF [§50.8(2)d] Not published 231 SF Surplus, justified as construction geometry
Unit circulation Unencumbered space per standard [§50.8(2)d] Not published "within two square feet of the requirement" ~Zero
Therapeutic and negative-pressure medical cells No IAC minimum for these unit types None 14-bed therapeutic unit; two 3-person negative-pressure medical units Above minimum by design choice (clip 3697, 27:26)

† The 70 SF total-floor-space floor [§50.8(1)a] and 35 SF unencumbered-per-occupant minimum [§50.8(1)b] both apply when confinement exceeds 10 hours per day, except during administrative segregation or emergencies. Jail housing meets that condition. The dayroom 35 SF figure [§50.8(2)d] is a separate requirement measured per prisoner exclusive of fixtures. Three distinct standards share the same number; they are not interchangeable.

Context: Iowa’s new-construction standard for multi-occupancy cells has become less demanding over time. The rule in effect from 1984 to 2005 (§50.6) required 120 SF gross for a two-person cell (70 SF for the first prisoner + 50 SF each additional). The 2005 rule (§50.8) replaced that gross measure with an unencumbered-space standard and introduced the confinement-hours condition, producing the 92 SF gross design. The new jail’s two-person cells are smaller than what Iowa required for new construction through 2005.

Lewis presented the dayroom surplus as construction geometry, not amenity: bending the units into the sawtooth roofline would create corners, corners "create safety risks," and the straight layout carries "advantages from a construction and cost standpoint." On circulation, Lewis said the design is "within two square feet of the requirement … we try to be more exact than that." The one stated margin above the code floor is the ceiling: 8 feet against a 7-foot minimum.

The sheriff's-office side

No code sets minimum sizes for sheriff's-office space. The July 9 schematic includes:

  • A 1,070 SF fitness room, about double the current ~500 SF.
  • A 5,000 SF locker and wellness block sized for 130 staff, the full roster. Asked for a shift-based calculation, Lewis could not state one.
  • A situation room and adjacent conference room totaling more than 2,000 SF.
  • 1,000 SF of unassigned space. Supervisor Sullivan: "It doesn't bother me to have an extra thousand square feet."
  • A 750 SF armory.
  • An 8,000 SF storage building.

The design language for this half of the building is growth. Lewis: "This is planned for growth. It's planned to be flexible." Sullivan: "a building that's going to last 100 years." Sheriff Kunkel: "spaces that we need not only today, but that they're going to need in the future."

Minimums vs. as designed

Building to the legal floor is lawful. It is also cheaper per bed than exceeding it. The county's bond-site homepage criticizes the current jail's 70 SF single cells — but the new single cells are the same 70 SF. That is the floor Iowa law sets for any new jail built for confinement exceeding 10 hours per day. See the fact-check entry on cell size.

Three claims about the same square footage

First, the jail side is built to the state floor. The table above shows zero margin on cell size and circulation and one foot on ceiling height.

Second, the County presents that floor as cost discipline. Kunkel, July 9: "What we have here is a responsible plan."

Third, the County markets the project as a major improvement for the people held there. The ordinary housing units deliver the state minimum. What incarcerated people get above the 1981 building is the floor any new Iowa jail must meet.

Some inmate-facing elements do exceed the minimums: a 14-bed therapeutic unit, two three-person negative-pressure medical units, and the dayroom surplus, which exists for construction geometry. These are real but narrow. The discretionary comfort and growth space in the building sits on the staff side.

The July 1 packet puts jail functions at 45 percent of the 118,500 SF. The Iowa Administrative Code sets per-cell square footage only. It does not set the bed count, which is a policy choice, and it sets nothing on the sheriff's-office side.

Part 4

The $69.4M Savings Claim

”≈$0”
Shive-Hattery’s $69.4M “savings” shrinks to near break-even once any financing is counted — at the adopted $94.5M bond and the county’s 12-year financing scenario, Build New and the forced-closure scenario cost roughly the same over 20 years

The $69.4M figure comes from Shive-Hattery's Supplemental Life Cycle Cost Analysis (July 2024). It is the difference between two projected 20-year scenarios:

  • Build New: construct the 140-bed jail plus Sheriff's Office ($79.75M combined / $48.88M jail-only), operate with 24 staff.
  • "Do Nothing" (forced-closure scenario): close the existing jail, build a holding facility ($13.6M–$50M), house all people held out of county at $60/day plus 2% annual inflation, operate an 18–30 staff transport unit.

Shive-Hattery's "Do Nothing" label describes a forced-closure scenario in which the existing jail is taken offline and all people held out-of-county. The County has not made that closure decision, no regulatory order requires it, and the existing jail's State Inspector record shows zero non-compliance items in both 2025 and 2026. This is a forced-closure comparison, not a comparison to the current status quo.

The actual annual OoC spend is $440K–$800K. The forced-closure scenario projects $4.8M/year on average. That gap is not because OoC rates are wrong — it is because the scenario assumes all ~83 current people are transferred out, not just the ~22 who are currently housed elsewhere.

How the savings figure changes with the actual bond amount

Shive-Hattery's Life Cycle Cost Analysis contains no debt service at all — no term, no interest rate. The $69.4M savings is a comparison of lump-sum capital plus 20-year operating costs. Once any financing is added, the savings collapse. The table below applies the county's 12-year financing scenario (Piper Sandler matrix, July 29, 2026: total interest = 32% of principal at a 4.45% all-in cost) with the operating component derived from Shive-Hattery's $212M anchor row: $212M − $48.88M lump-sum capital = ~$163M operating over 20 years.

aria-label="Savings sensitivity to bond amount (12-yr county scenario, operating from SH anchor)">
Capital basis Build New 20-yr total Forced-closure 20-yr total Difference
$48.88M (Shive-Hattery Vol I, anchor) ~$228M ~$282M Forced-closure +$54M
$79.75M (Shive-Hattery Supplemental) ~$268M ~$282M Forced-closure +$14M
$94.5M (adopted bond) ~$288M ~$282M Build New +$6M (roughly break-even)

Build New 20-yr total = (capital basis × 1.32, the 12-year scenario's principal-plus-interest ratio) + $163M operating. Forced-closure total held at Shive-Hattery's stated $282M. The $94.5M bond covers jail + Sheriff's Office; the $48.88M anchor is jail-only — the scopes do not cleanly align, so the exact break-even figure carries uncertainty in both directions. At 20-year amortization (interest $51.6M per the same matrix), Build New at $94.5M ≈ $309M — about $27M more expensive than forced-closure.

The "$69.4M savings" claim is entirely an artifact of using the Vol I $48.88M planning estimate as the capital basis, and of omitting financing costs entirely. At the adopted $94.5M, once the county's own financing scenarios are counted, Build New and the forced-closure scenario are roughly the same cost over 20 years — and Build New is the more expensive option at any term of 15 years or longer.

The undisclosed population assumption

The forced-closure scenario projects $89.3M in per-diem costs over 20 years. The document states three inputs for this figure: 83 people/day, $60/day starting rate, and 2% annual inflation. Those three inputs do not produce $89.3M — they produce approximately $44.7M. At least one input must differ from what is stated. There are three possible readings:

If this variable is adjusted… …it must equal Notes
Population (rate and inflation fixed at stated values) ~170 people/day Double the stated 83/day; exceeds Build New design maximum of 140
Average per-diem rate (population fixed at 83/day) ~$147/day average over 20 years Requires rates roughly 2× the Linn agreement; or an inflation assumption near 8.5%/year rather than stated 2%
Inflation rate (population and starting rate fixed) ~8.5%/year More than four times the stated 2% assumption

The document does not disclose which variable was adjusted or why. All three readings require an undisclosed departure from the stated inputs.

The population reading (170/day) has an additional internal inconsistency: Shive-Hattery sized the Build New facility for a maximum of 140 people (120 permanent beds + 20 flexible). The same consultant cannot simultaneously project 170/day future need for the forced-closure scenario and design Build New for a 140-bed maximum — the facility would be undersized on day one of its intended use. If 170/day is the correct population assumption, the ~$288M Build New 20-year total at $94.5M is still understated, because the facility would require a second expansion before the 20-year period ends.

If the stated 83/day population is correct instead, the forced-closure scenario's 20-year per-diem is approximately $44.7M — and the forced-closure 20-year total falls from ~$282M to ~$237M. At the adopted $94.5M, Build New (~$288M) would be approximately $51M more expensive than that corrected forced-closure total over 20 years.

Part 5

Debt Service

$30.2M
total interest under the 12-year scenario the Board discussed — but the term is set after the election, and the county's matrix runs from $25.0M (10 years) to $51.6M (20 years)

Johnson County's existing bonds are nearly paid off. The FY27 Tax Calculation Worksheet shows the Debt Service Fund (Fund 65) with FY27 tentative revenues of $36,038 — effectively zero. The county is at or near the end of its current bond obligations.

The term history runs through three stages. On June 10, 2026, Chair Green presented Finance Director Dana Aschenbrenner's $107/$100K figure on a 10-year, 5.5% basis. Aschenbrenner's later written summary (July 29, 2026 work session packet) describes those assumptions as intentionally "aggressive": his goal was "to set a 'ceiling' that I could confidently state regardless of the ultimate financing terms agreed upon." On July 29, Piper Sandler & Co. presented a maturity matrix — eleven scenarios, 2037 to 2047 final maturities, at market-based yields of 4.17% to 4.49%. On August 5, Green announced that he and Supervisor Sullivan had "settled on a 12-year repayment"; Green-Douglass pressed for 15 or 20 years and then accepted 12; Fixmer-Oraiz and Remington opposed. The 12-year term was never placed in the resolution, the notice, or the ballot. The notice explicitly states its estimate on property taxes is based on a repayment term that is subject to change. Iowa Code §76.1 caps GO retirement at 20 years from issue; §76.2 requires a levy resolution naming a repayment period before issuance — a post-election decision by whichever board then sits.

Final maturity Term Est. yield / all-in cost Total interest Annual per $100K taxable
6/1/2037 10 yr 4.17% / 4.33% $25.0M $101.22
6/1/2039 12 yr 4.31% / 4.45% $30.2M $88.00
6/1/2042 15 yr 4.41% / 4.52% $38.0M $74.81
6/1/2047 20 yr 4.49% / 4.58% $51.6M $61.86

Source: "summary of options with tax impacts 2026-07-23 v2," July 29, 2026 work session packet (Granicus clip 3736), p. 9. Download the packet (PDF), including the Finance Director's Executive Summary. All rows assume $94.5M borrowed against the FY27 debt-service taxable valuation of $11.81B with zero valuation growth for the full term — a conservative assumption; the county's worksheets show the base grew 3.57% (FY26) and 4.71% (FY27). Estimated proceeds available for construction are ~$94.9M in every row: the term choice changes what taxpayers pay, not what the project receives. Bonds are callable from 2033–2035 depending on scenario. Costs of issuance ($744,100, including the Piper Sandler fee) are paid from bond proceeds.

What the ballot and notice do not say

The proposition voters will see is fixed by statute — §331.442(2)(b) prescribes the form, with blanks only for the county name, amount, and purpose — so interest could not lawfully appear on the ballot. Fixmer-Oraiz's August 6 amendment to add "an additional $30,000,000 in interest" failed 2-3 on bond-counsel advice, and on the ballot form the advice had a statutory basis. But the notice, the county's website, and its fact sheet are not statutorily constrained, and none of them states a term, a rate, or an interest total. Five things a yes vote authorizes that no county document tells voters:

  1. The levy is mandatory (§76.2) and sized to principal plus whatever interest results; §76.3 says a bond proposition's dollar limit restricts only the amount of bonds issued, not the taxes levied. The total authorization is therefore roughly $120M to $146M at the matrix's assumed rates, wider if rates move before pricing.
  2. The 12-year figure is a two-supervisor agreement recorded in work-session minutes. The notice itself says the estimate "may be adjusted down depending on the final repayment schedule." The named mechanism for lowering the annual figure, a longer schedule, raises the total cost: 15 years adds $7.8M of interest over the 12-year scenario, 20 years adds $21.4M. Publishing a planning term is neither difficult nor unusual: the City of Urbandale's information page for its November 3 bond includes it (published July 1, 2026; retrieved August 11).
  3. The notice's $88.00 was computed per $100,000 of taxable value and recited per $100,000 of actual value. The difference is the 47.4% residential rollback. See fact check.
  4. The notice calls the estimate "the maximum taxpayer cost"; the Finance Director told the Board the published figure "establishes the maximum amount that may be levied." §331.442 calls it an estimate; neither ch. 75 nor ch. 76 makes it a cap; Ahlers & Cooney's client guidance on the disclosure law describes it as a disclosure. No legal authority for the ceiling claim has been cited in any county document.
  5. "Acquiring land" is an adopted bond purpose; the ~$2.1M IWV/Slothower parcel was bought from reserves in July 2026 and could be reimbursed from proceeds after passage.
Part 6

The Land Is Being Bought Outside the Bond

~35 ac
IWV Rd SW & Slothower Rd, Iowa City
purchased July 2, 2026, 5-0
~$2.1M
~$60,000/acre from County reserves (cash), not the bond
(acreage pending survey/replat; total is approximate)
$0
Amount of the $94.5M bond that has been voted on
(Resolution 08-06-26-03 sets the vote for Nov. 3, 2026) Amount of the $94.5M bond that has been voted on
(Resolution 08-06-26-03 sets the vote for Nov. 3, 2026)

On July 2, 2026, the Board of Supervisors voted 5-0 to approve a definitive purchase agreement for approximately 35 acres at the SW corner of IWV Road SW & Slothower Road, inside Iowa City limits. The price is $60,000 per acre of gross land area — approximately $2.1M total, with the exact figure to be set once a survey and replat record the final acreage. The purchase is funded entirely from County reserves; it is not part of the $94.5M bond. reserves; it is not part of the $94.5M bond.

The ballot proposition names "acquiring land"

The adopted ballot proposition (Resolution 08-06-26-03, August 6, 2026) authorizes bonds "for the purpose of acquiring land and constructing, equipping and furnishing a new sheriff's office and jail facility." Land acquisition is a named purpose of the $94.5M bond — yet the actual site was acquired first, from reserves, before any vote. Land acquisition is a named purpose of the $94.5M bond — yet the actual site was acquired first, from reserves, before any vote.

The most likely mechanism is reserve-then-reimburse: the County fronts the purchase from cash and, if the bond passes, reimburses reserves from bond proceeds. No document confirms this for this specific purchase; it is an inference. The County has done it before: the FY25 budget included "$1,044,000 Bond Proceeds for Affordable Housing" reimbursing an earlier reserve outlay. The May 6, 2026 draft ballot Options 1 and 2 expressly listed "refunding pre-development costs" as a bond purpose, which would have covered the ~$2.9M in documented pre-bond consultant spending and construction commitments paid from current funds. The adopted proposition names "acquiring land" but dropped "refunding pre-development costs" — so the land can be reimbursed from proceeds; the consultant spending cannot, absent a broader reading of the construction purpose. current funds. The adopted proposition names "acquiring land" but dropped "refunding pre-development costs" — so the land can be reimbursed from proceeds; the consultant spending cannot, absent a broader reading of the construction purpose.

The bond vote is a waivable contingency

The purchase agreement includes a bond-referendum contingency, but contingency (i) allows the County to waive it: passage of a referendum "may be released by Buyer and Buyer may elect to proceed to Closing notwithstanding, and at any time before or without, the holding of any such referendum." The County can close whether the bond passes, fails, or is never held.

At the public meeting, Supervisor Fixmer-Oraiz voted for the purchase as "a land option and not for any particular specific purpose." Chair Green described the jail as "the most likely outcome … regardless of what ends up being developed there, if anything." The executed contract warrants the County's ability to "use and develop the Property for its intended governmental purposes, including a County jail and sheriff's office." The purchase agreement is available for download on the Records page.

Price, assessed value, and the easement

The County is paying approximately $60,000/acre. The Iowa City Assessor's 2025 reassessment values the land at approximately $31,590/acre (all land; $0 improvements). The last recorded sale was May 13, 2021: $2,450,880 for the whole tract, implying roughly $60,000/acre if the parcel was approximately 40 acres at that time. Both figures are in the public record.

The agreement includes a 350-foot vegetative buffer easement, plus other easements and rights-of-way, counted in the gross acreage but limiting the area the County "may lawfully construct" on. The 35-acre figure is gross area, not buildable area.

The subdivision structure

The seller, IWV Holdings, LLC, owns a two-lot subdivision recorded as IWV Commercial Park. The County is buying Lot 1, which the agreement describes as the current Lots 3–8 of Melrose Commercial Park, to be replatted as Lot 1 of IWV Commercial Park. The seller retains Lot 2. Lot 1 is approximately 61% of the subdivision by area; Lot 2 is approximately 39%. The shared grading and detention-basin costs are split in that proportion. The detention basin sits on Lot 1 and serves both lots.

Costs and constraints beyond the purchase price

The $60,000 per acre is for gross land. The agreement's Land-Use Obligations article assigns the County additional costs and limits how much of the parcel can be built on.

After the buffer, the detention basin, and internal roads and setbacks, the buildable area is likely in the low 20s of acres rather than 35. The 61.04% shares of grading and basin construction are separate from the $60,000 per acre. The exact buildable acreage and grading cost depend on the recorded plat and the approved subdivision construction plans, which have not been published.

The Iowa City Assessor lists the property as Class "C - Commercial," noted explicitly as "for tax purposes only. Not to be used for zoning." The purchase agreement requires Iowa City approval "including any necessary re-zoning and site plan approval" (contingency (j)) before closing. The parcel is inside Iowa City's corporate limits; the city holds full zoning authority.

The joint jail project collapsed in September 2025 when Iowa City's Mayor vetoed a proposed Riverside Drive site after a 4-3 City Council vote. The current purchase is contractually contingent on that same city's approval.

This parcel is immediately south of the Historic Poor Farm (4811 Melrose Ave, Iowa City), in the same far-western corridor the Board rejected as a jail site on April 22, 2026. Supervisor Sullivan cited "transportation challenges" among the reasons for that rejection. A bond rationale the County has cited is keeping incarcerated people near family — Bill Waldie (July 2, 2026): "so they're near their folks, near their family." No written transit or accessibility requirement for site selection has been identified in a primary source; this note will be updated if such a document is found.

Part 7

Status Quo vs. New Facility

+$9.6M/yr debt service alone
new facility average annual debt service (~$10.4M, 12-yr scenario) minus FY27 OoC budget saved ($800K) — full all-in annual cost unknown; reference point if operating costs hold flat: ~$16.8M/year

The Shive-Hattery analysis frames the choice as Build New (~$212M over 20 years) versus the forced-closure scenario (~$282M over 20 years). Neither scenario represents continuing to operate the existing jail.

The County FY27 budget projects continued operation of the existing jail with $800,000 in OoC overflow. Shive-Hattery's forced-closure scenario projects $4.8M/year average on the same line item — 6× the County's actual operating-plan figure — because the consultant assumes the jail closes and everyone moves out. The County is not planning to do that.

Scenario Annual cost basis
Current status quo (FY27 budget, function 1050) ~$7.2M/year (incl. $800K OoC)
New facility — debt service only ($94.5M, 12-yr scenario) ~$10.4M/year average
New facility — operating costs Not published — no pro-forma operating budget has been released
New facility — all-in reference point (debt service + current JoCo operating at flat cost) ~$16.8M/year (~$10.4M debt + $6.4M operating — operating costs held flat at current $6.386M; no new-facility pro-forma available)
Forced-closure scenario / all OoC (annualized from 20-yr total) ~$14.1M/year

The new facility eliminates perhaps $440K–$800K/year in OoC costs while adding ~$10.4M/year in average debt service (12-year scenario; ~$7.3M at 20 years, with $21M more total interest). The net debt-service burden relative to today is approximately $9.6–10.0M/year depending on whether the FY27 budgeted OoC figure ($800K) or the FY25 actual ($440K) is used as the baseline. Shive-Hattery has not published a pro-forma operating budget for the proposed facility, so the all-in annual cost cannot be calculated from available primary sources. As a reference point: if total operating costs held flat at the current $6.386M/year (most costs are personnel — you don't reduce staff simply because more people arrive), total annual cost would be approximately $16.8M/year (~$10.4M debt service + $6.4M operating). Whether the new facility achieves lower per-person operating cost depends on assumptions that have not been disclosed.

The Shive-Hattery analysis does not present this comparison. The document's Build New figure (~$10.6M/year annualized at their $48.88M basis) already represents a ~47% increase over the current operating baseline — not a savings relative to today. At the adopted $94.5M, that annualized figure rises further.

Johnson County Sheriff's Office general-fund budget, FY24–FY27 +61% over 5 years (FY22 actual → FY27 proposed) $0M $5M $10M $15M $20M $11.62M FY22 actual $12.3M +6% FY23 actual $13.44M +9% FY24 actual $15.3M +14% FY25 actual $17.6M +15% FY26 adopted $18.67M +6% FY27 proposed Actual Adopted Proposed
Sheriff's Office general-fund budget, FY22–FY27. The +61% increase from $11.62M (FY22 actual) to $18.67M (FY27 proposed) precedes any bond-funded construction. Bond debt service and new facility operating costs would be on top of this baseline.
Part 8

Transport, Staffing, and Composition

Scope beyond the jail

The Shive-Hattery Vol I Needs Assessment (§IV.E / Appendix E) documents the full space program: a replacement Sheriff's Office, training facilities, courtrooms and offices for the County Attorney and other staff, and approximately 12,000 SF of Vehicle Maintenance and Storage for law-enforcement fleet repairs. Vol I does not reference the existing County Fleet Shop.

At the April 24, 2025 formal Board of Supervisors meeting (Granicus clip 3174), the Board passed a resolution for the "Fleet Shop Expansion Project, located at 4810 Melrose Avenue, Iowa City" — three additional bays, designed by Vantage Architects, estimated total cost $1,325,000, bids solicited May 15, 2025. The IWV/Slothower parcel fronts Melrose Avenue (purchase agreement, access clause), placing the proposed new building across the street from the fleet shop just expanded. The proximity is verifiable on an aerial or parcel map.

At the July 9, 2026 CJCC meeting, the County confirmed the overlap and removed the program from the building. Lewis said vehicle maintenance "is essentially now across the street or in your current facilities." Supervisor Green-Douglass said the program was removed "because across the street we have vehicle maintenance."

The deletion did not shrink the building. Total floor area stayed at 118,500 SF; the deleted program's space became mechanical rooms, loading, and unassigned area.

Overcrowding is a declining share of transports

The County's 2025 transport snapshot reports 484 of 1,211 transports (40%) as overcrowding-driven.

Infographic with Transportation Costs by Year
Out of County Inmate and Transportation Costs 2001–2025, Johnson County Sheriff's Office.
Year Total Overcrowding Share Source
202273942657.7% Sheriff's FY26 Budget Presentation, slide 11
202382738346.3% Sheriff's FY26 Budget Presentation, slide 11
202475431341.5% Sheriff's FY26 Budget Presentation, slide 11
20251,21148440.0% "Out of County Inmate Housing and Transportation Costs" infographic, 2025

The 2022–2024 data uses three categories (Jail Transfers, Mental Transports, Transport Court Order). The 2025 infographic uses five — adding Warrants (228) and Juvenile (109) categories that mechanically reduce overcrowding's percentage share without changing the absolute count. Overcrowding-driven transports peaked at 426 in 2022, fell to 313 in 2024 (a 27% decline), and rebounded to 484 in 2025 — tracking the Linn County contract ramp-up. None of this is broken out in the Sheriff's 2025 infographic.

30
FTE required under forced-closure scenario — 6 more than building a new jail, to move people to places that still charge $89.3M

The forced-closure scenario is sometimes read as a lean fallback. The staffing numbers say otherwise.

Scenario Staff Role
Build New 24 Operate 140-bed jail
Forced-closure 18 Transport unit — transfer 83 people to other counties daily
Forced-closure +12 Operate intake/holding facility
Forced-closure total 30 25% more than Build New

Shive-Hattery describes these 30 positions as a minimum: "FTE's staff positions will increase as transportation growth occurs due to inefficiency and capacity issues of existing facilities." Those 30 positions cost ~$145M over 20 years — more than the $96.3M in OoC housing they exist to manage. Johnson County would also pay both the per-diem ($89.3M) and the transport logistics ($7M) as separate line items.

The document explicitly excludes liability from the model: "The scenarios projected do not consider the increased liability concerns associated with transporting people to other facilities. Liability is a significant factor for consideration in future evaluations, both for staff and incarcerated people." This is the only scenario-specific cost that carries a formal disclaimer.

FTE's staff positions will increase as transportation growth occurs due to inefficiency and capacity issues of existing facilities.

Shive-Hattery Supplemental Life Cycle Cost Analysis, p. 2 (July 2024)

Staffing numbers

Four staffing figures for the jail and the Sheriff's Office are given:

Figure Description Source
24 Baseline positions for the 140-bed plan; Vol. I states "no additional staff will be needed" Shive-Hattery Vol. I, August 2024
30–35 Staff "working back in the jail" Michael Lewis, CJCC meeting, July 9, 2026
41 Current jail staffing: 29 full-time deputies plus 8 full-time and 4 part-time non-sworn State inspection form, January 2026
~120 Sheriff's Office employees county-wide ("a full 20% of" ~600 county employees) Supervisor Sullivan, July 16, 2026

Vol. I plans 24 positions for a 140-bed facility; the State counted 41 people staffing the current jail. Nothing published says whether the ~17-position difference is cut, reallocated, or absorbed, and no first-year staffing budget for the new facility has been released.

Supervision model does not explain the differences. Vol. I states: "Podular-indirect supervision has been selected as the preferred method." The current jail is not direct supervision, and neither is Washington County's; the same State inspector marked both accordingly. With the supervision model constant across all three, the staffing-cost variable is the deputy-versus-non-sworn choice. Washington County operates an 84-bed jail and the county dispatch with 16 non-sworn staff.

The 5,000 SF locker and wellness block in the proposed building is sized to the full roster of about 130, not to on-site attendance. Jail shifts run 6 to 8 staff on days and 4 to 7 at night, per the State inspection form. Asked for the calculation behind the 130, Lewis said he would have to look it up. A hardened storm shelter is cited as a code driver for the block; that requirement covers hardening, not program size. The specific code section has not been verified.

Is the 18 transport FTE estimate defensible?

The figure is stated in one sentence with no supporting breakdown. The current baseline, from the Sheriff's Programming Questionnaire (Vol I Appendix, p. 101), is four part-time transport drivers for a ~56-person in-house population with ~22 people held out of county. The forced-closure scenario calls for 18 FTE. The raw headcount rises from 4 to 18 (4.5×), but the comparison also involves a change in position type — from part-time to FTE — which typically carries a different cost structure. Neither the Vol I Appendix nor the Supplemental discloses the compensation basis for the current part-time positions or for the proposed 18 FTE: no hourly rate, salary range, or benefits eligibility is stated for either. The true cost difference between the current baseline and the forced-closure staffing model is therefore larger than headcount alone indicates, but by how much is not established in any published document.

An independent check using the NIC Staffing Analysis Workbook methodology — which Shive-Hattery itself uses for the Build New staffing calculation — yields a range of 15–22 FTE for a full-closure scenario with 83 ADP distributed across multiple counties, applying a standard two-officer minimum per vehicle (per ACA standards as incorporated in USMS Federal Performance-Based Detention Standards, and consistent with Shive-Hattery Vol. I staffing methodology) and standard single-watch shift relief factors. The 18 FTE figure falls within that range and is not obviously inflated. However:

Part 9

The 2018 ADA Audit

The county's bond site cites a 2018 accessibility evaluation as evidence the jail "does not meet accessibility guidelines of the Americans with Disabilities Act." WT Group inspected the building on November 29, 2018, and delivered a 260-page report on February 3, 2019, with 166 numbered findings. Read the full report (PDF).

What was actually audited

The report is organized into area sections, each covering a run of numbered findings:

Area Findings
Parking1–4
Interior accessible route (stairwells, elevator, ATM)5–25
Restroom lobbies (women's, men's)26–41
Offices42–130
Men's locker room131–140
Women's locker room141–149
Jail (kitchen, control room, support spaces)150–166

The section labeled "Jail" is the report's last section and its smallest claim on the word: every finding in it is the kitchen, the kitchen restroom, the jail control room, or a stairwell and sink in those spaces. None of the 166 findings mentions a holding cell, a housing cell, an inmate shower, a dayroom, or the booking area, and none cites 2010 ADA Standards §232, the detention-facilities section that sets the minimum accessible-cell count. The secure housing units — where the people the county says the audit concerns actually live — were not inspected.

What the findings recommend

Of the 166 findings, at least 43 are deferred: "leave as is, employee work area pursuant to 2010 Standards 106.5 Defined Terms, until an employee with a disability works here." At least 11 more findings report the element already compliant, with a recommendation of "None." The remaining roughly 110 findings call for an actual fix.

Some of those fixes are minor and cheap: repainting a parking access aisle to 5 feet (as-built 51 inches), adjusting door closers to 5 lbf, relocating a protruding towel dispenser, remounting a thermostat or hook into reach range, insulating lavatory pipes. Others are structural and real, and the county's strongest reading of the audit rests on these: door maneuvering-clearance and 30-inch door-width deficiencies recur across dozens of findings; at least three rooms have insufficient turning space; at least three restrooms are flagged "not nearly compliant," missing required clear floor space and grab bars (findings 48, 81, 152); neither staff locker room has an accessible shower (findings 140, 144); there is no accessible route to the mechanical room, reachable only by a steep interior stairway (finding 128); and the elevator is missing a compliant audible signal, visible signal, and jamb-mounted floor star (findings 17–19).

The unpublished transition plan

The report's cover letter defines five remediation phases and states that phase assignments for each finding exist in "an Excel document that is easily modified... and easily searched in many different ways." The sheet is not part of the published PDF and has not otherwise been made public. Phase 1 is defined as findings that "should be completed immediately... little or no cost, were in violation of the codes at the time of construction, or pose an imminent safety threat." Whether any findings have been remediated in the seven years since the report is unknown; the inclusion of the report on the jail bond website suggests no remediation. A records request for the transition-plan spreadsheet and any remediation invoices since February 2019 is outstanding (see the Records page, RR-009).

The legal standard under Title II is program access, not full-facility compliance, and the bond site's framing does not draw that distinction.

Part 10

Data Gaps

The following information would materially change the analysis if it were available and has not been published or produced in response to open-records requests as of August 2026: open-records requests as of August 2026: